DGS: Office of Public School Construction: All Propositions Summary

Program Accomplishments
The statewide bond funds provided under School Facility Program represent tremendous accomplishments for the students of California.

These charts summarize the K-12 facilities funding provided in Propositions 1D, 55, 47, and 1A:


* Mouse over to enlarge 

Program Amount
Authorized
Amount
Funded
Balance Pupils Housed
in New
or Modernized
Classrooms
Classrooms Number
of
Projects
New Construction  $16,010,000,000  $14,954,564,377  $1,055,435,623  1,092,783  42,030  2944
Modernization  $10,950,000,000  $8,705,763,786  $2,244,236,214  2,524,962  97,114  5114
Career Technical Education  $500,000,000  $205,342,794  $294,657,206      181
High Performance Schools  $100,000,000  $10,917,367  $89,082,633      
Overcrowding Relief  $1,000,000,000  $39,953,524  $960,046,476      
Critically Overcrowded Schools  $4,140,000,000  $2,768,634,795  $1,371,365,205  99,802  3,839  799
Charter School  $900,000,000  $717,440,478  $182,559,522  12,103  466  34
Joint Use  $129,000,000  $128,380,259  $619,741      175
Hardship  $1,000,000,000  $954,867,233  $45,132,767      
Class Size Reduction  $700,000,000  $472,931,638  $227,068,362      
Total:  $35,429,000,000  $28,958,796,251  $6,470,203,749  3,729,650  143,449  9,247

All Proposition Funding Highlights
Total Amount Authorized  $35,429,000,000  
Total Amount Funded  $28,958,796,251  
Total Remaining Balance    $6,470,203,749
Statewide Cost  $32,529,122  
Administrative Cost  $106,665,900  
Total Statewide & Administrative Cost    $139,195,022
Total Funds Available    $6,331,008,727